Click the Play button to listen to article

The Supreme Court on Tuesday (August 18) ruled against judicial interference in public procurement tenders at an advanced stage, noting that a belated challenge to tender conditions, after significant developments had taken place in the evaluation process, would be unfair and unjust to otherwise eligible bidders.

A bench of Justice KV Viswanathan and Justice Arun Palli dismissed appeals challenging tender conditions for procurement of sports goods and outdoor gymnasium equipment for government schools in Delhi, noting that the process had substantially advanced and third-party rights had crystallized.

“Judicial discretion, therefore, must be exercised with extreme circumspection to ensure that fence–sitters, proxies, and unscrupulous litigants who bring a challenge at an advanced stage, are not allowed to disrupt an ongoing process.”, the Court observed.

Noting that despite the Appellants having a notice of the tender conditions from the inception of the tendering process, chose to remain silent for four months, before challenging the tender conditions on the grounds of being excessive, exclusionary and arbitrary before the High Court. When the challenge to the tender was made, substantial development took place, including the crystallisation of a third-party rights, which the Court found to be prejudicing the rights of the successful bidders.

The court noted that the Sports Equipment Tenders were floated on December 22, 2025, with the bidding deadline being January 13, 2026. However, the writ petition challenging the tender conditions was filed only on April 1, 2026, about four months after publication. By then, one of the six sports equipment tenders had already been awarded, while the remaining tenders had moved through document verification and physical demonstration stages and had reached financial evaluation by the time of the Supreme Court's consideration.

“Tender schedules operate within compressed and purpose – bound timelines. Four months may appear modest when viewed merely as a measure of calendar time. In the life of a tender, however, it may mark the distance between invitation and evaluation, between evaluation and selection, and between an open field and the crystallization of competing interests. Delay in such matters is therefore not assessed by counting days alone. It must be assessed by reference to what has occurred during those days, whose interests have arisen, and what public consequences would follow from unsettling the process at that stage.”, the judgment authored by Justice Palli observed.

Tendering process cannot be stalled at the verge of final evaluation of the price bids

“Those who participated in the tendering process, met every single condition/eligibility criterion, and went through a rigorous evaluation of their technical bids were declared responsive/compliant. Such entities, at the verge of final evaluation of their price bids, too have acquired certain rights and interests. Therefore, to stall the process and afford any judicial indulgence to the Appellants, who approached the High Court at their own convenience, would be unfair. Rather unjust.”, the Court said.

The court further held that a challenge to an eligibility condition accrues on the very day the condition is published. A bidder who considers itself excluded or rendered ineligible by an allegedly arbitrary condition must raise the grievance at the earliest opportunity.

The Supreme Court also attached particular significance to the public purpose behind the tenders. The procurement involved sports and gym equipment worth around ₹34 crore, intended for approximately 16 lakh school students. A substantial portion of the procurement had come to a standstill because of the litigation, the court noted.

The bidders had particularly challenged a condition requiring sports equipment suppliers to maintain a fully functional office in Delhi and a warehouse in Delhi/Delhi-NCR for the previous three years.

The clause stated that the requirement was imposed because the department might require equipment to be supplied at short notice.

The appellants argued that the condition was exclusionary and relied on the Supreme Court's 2025 decision in Vinishma Technologies Pvt. Ltd. v. State of Chhattisgarh, where a tender condition requiring prior supply experience specifically to State government agencies in Chhattisgarh had been held arbitrary and discriminatory.

The Supreme Court, however, distinguished that decision. It noted that the Delhi condition was presented as an operational requirement, intended to ensure prompt installation, inspection, servicing, maintenance and replacement of equipment, particularly because delays concerning defects or safety could affect schoolchildren.

As a result, the appeals were dismissed.

“…the Appellants' case is bereft of any merit, it is for this belated challenge, portraying a lack of bona fide that we are dissuaded from examining the assailed clauses, rendering any findings on the same, and hence lie on the same page as the High Court.”, the Court held.

Cause Title: M/S. UTKARSH ENTERPRISES & ORS. VERSUS UNION OF INDIA & ORS.

Citation : 2026 LiveLaw (SC) 825

Click here to download judgment

Appearance:

For Petitioner(s) Mr. Raju Ramachandran, Sr. Adv. Mr. Ejaz Maqbool, AOR Ms. Aanchal Basur, Adv. Ms. Shruti Narayan, Adv. Mr. Zain Maqbool, Adv. Ms. Raji Gururaj, Adv. Ms. Nida Khan Salim, Adv. Mr. Meeran Maqbool, Adv. Mr. Saif Zia, Adv.

For Respondent(s) Ms. Swati Ghildiyal, AOR Ms. Sonakshi Sinha, Adv. Ms. Shweta Bharti, Adv. Ms. Tejaswini Chandrasekhar, Adv. Mr. Jatin Chaddha, Adv. Mr. Abhinav Agrawal, AOR Mr. Piyush Bhardwaj, Adv. Mr. Shivam Sengupta, Adv.

Tags: