CERC's Powers To Refer Disputes To Arbitration Extends To Even Those Cases Which Fall Outside Its Jurisdiction: Delhi High Court

Update: 2025-11-13 09:15 GMT
Click the Play button to listen to article
story

In a noteworthy judgment for the renewable energy sector, the Delhi High Court has observed that the power of Central Electricity Commission (“CERC”) under Section 79(1)(f), Electricity Act to refer parties to arbitration is wider than its power to adjudicate. A bench of Justice Purushaindra Kumar Kaurav observed that CERC in exercise of its adjudicatory powers can...

Your free access to Live Law has expired
Please Subscribe for unlimited access to Live Law Archives, Weekly/Monthly Digest, Exclusive Notifications, Comments, Ad Free Version, Petition Copies, Judgement/Order Copies.

In a noteworthy judgment for the renewable energy sector, the Delhi High Court has observed that the power of Central Electricity Commission (“CERC”) under Section 79(1)(f), Electricity Act to refer parties to arbitration is wider than its power to adjudicate.

A bench of Justice Purushaindra Kumar Kaurav observed that CERC in exercise of its adjudicatory powers can only adjudicate upon disputes connected with Section 79(1)(a)-(d). However, while exercising its referral powers, it can refer “any dispute” for arbitration, even those upon which it cannot adjudicate.

Facts

The Petitioner, Renew Wind Energy (Ap2) Pvt Ltd. (“Renew”) a power generating company, filed the present petition under Section 9, Arbitration and Conciliation Act, 1996 (“ACA”) praying for an order restraining/injuncting the Respondent, Solar Energy Power Corporation (“SECI”) from unilaterally deducting amounts from its monthly invoices.

Renew was a successful bidder and the parties executed a Power Purchase Agreement (“PPA”) dated 23.05.2018 for the supply of 300 MW of power for 25 years. On 02.05.2025, SECI issued a notice Renew stating that Renew had failed to fulfil the minimum energy requirement for the financial year 2024-25 and demanded 75% of the cost of shortfall as compensation under the PPA, failing which the applicable amount would be deducted from the next month's invoice (“Impugned Notice”)

Apprehending that SECI would take coercive measures before the constitution of the arbitral tribunal, Renew approached the Court seeking interim protection against the Impugned Notice and any consequential deductions. SECI filed a comprehensive reply, raising several objections, the main objection being the maintainability of the petition in light of Section 79(1)(f) of the Electricity Act, 2003 which provides the powers of Central Electricity Regulatory Commission (“CERC”) to adjudicate or refer disputes for arbitration.

Contentions

The Senior Counsel for the Respondent contended that disputes concerning tariffs must be adjudicated by the CERC. He further submitted that only the CERC can refer such disputes to arbitration, if at all it is necessary. It was also contended that Section 9, ACA is inapplicable in the instant case as Section 2(3), ACA excludes its application where another enactment such as Electricity Act applies. Further, Section 174, Electricity Act grants overriding effect to the Electricity Act over other laws, except those specified in Section 173, in case of inconsistency. Thus, the Electricity Act prevails over the Arbitration Act.

The Senior Counsel for the Petitioner submitted that SECI's attempt to bring the present dispute under the jurisdiction of CERC by invoking the concept of tariff under Section 79(1)(f) was flawed. Mere reference to tariff-related clauses in the PPA does not transform all contractual disputes into regulatory ones. The claim in the present petition was for damages for non-supply and not for modification or determination of tariff.

Further, the Counsel contended that there is a clear distinction between the adjudicatory powers conferred upon State Commissions and CERC. While the Electricity Act confers broad adjudicatory powers on State Commissions, the adjudicatory powers of CERC as provided in Section 79(1)(f) applies only to disputes that involve functions such as tariff regulation, scheduling and generation by central government- owned entities. Since the present dispute does not relate to these functions, the CERC has no jurisdiction.

Observations

The Court started its analysis by noting that a petitioner seeking interim measures/protections under Section 9 must establish a right to invoke arbitration proceedings. The Court also highlighted Section 2(3), ACA which considers the possibility of a special statute prevailing over ACA and providing for a different mechanism to deal with a particular category dispute. In the instant case, Section 79(1)(f) read with Section 174, Electricity Act makes ACA inapplicable to the present dispute.

The Court also clarified the true import of Section 79(1)(f), Electricity Act. The Court observed that while from a plain reading of the section it would appear that CERC is to exercise its functions of adjudication of disputes and referring them from arbitration simultaneously. But such an interpretation would be anomalous and so the word “and” in the section should be read as “or” meaning thereby that the powers are to be exercised in the alternative.

The Court further observed that Section 79(1)(f) is in two parts — the first part refers to the adjudicatory powers of the CERC and the second deals with the referral powers of the CERC. Importantly, the power to refer disputes for arbitration under the second part of the provision is broader than the power to adjudicate disputes. While the adjudicatory powers are restricted to disputes connected with matters enumerated under Section 79(1)(a)-(d), the referral power extends to ―any dispute involving generating companies or transmission licensee.

The referral power of CERC also has two facets – first is the power to refer such disputes for arbitration which the CERC is itself capable of adjudicating, these being disputes connected with clauses (a) to (d) of Section 79(1); and second, the power to refer a dispute for arbitration which it is not capable of adjudicating. In the first case, the power is discretionary as CERC can choose whether to itself adjudicate upon the dispute or refer the same for arbitration.

The second aspect of the referral power relates to the power of the CERC to refer such disputes for arbitration which fall outside the scope of Section 79(1)(a)-(d). Such a referral would take place when there exists an arbitration clause. In such a situation, while the CERC cannot adjudicate upon the dispute, it can nevertheless refer the same for arbitration. In fact, in such a case CERC is bound to refer the dispute to arbitration.

The Court also made a note of Section 94(2), Electricity Act which allows party to seek during the pendency of its petition under Section 79(1)(f), interim reliefs of the kind provided for in Section 9, ACA. Thus, Renew would not be remediless when the instant Section 9 petition is disallowed.

Thus, the Court found the instant petition to be not maintainable and dismissed it.

Case Title – Renew Wind Energy (Ap2) Pvt Ltd v. SECI

Citation: 2025 LiveLaw (Del) 1491

Case No. – O.M.P.(I) (COMM.) 213/2025

Appearance-

For Petitioner

Mr. Jayant Mehta, Sr. Advocate with Mr. Vishrov Mukherjee, Mr. Girik Bhalla, Ms. Sai Snigdha Nittala, Ms. Juhi Senguttuvan, Ms. Priyanka Vyas, Mr. Yashaswi Kant, Mr. Prayush Singh and Ms. Pallavi Arora Advocates, instructed by Trilegal

For Respondent

Mr. M.G. Ramachandran, Sr. Advocate with Ms. Anushree Bardhan, Ms. Srishti Khindaria, Ms. Somya Sahni, Ms. Ritika Singh and Mr. Aneesh Bajaj, Advocates

Date – 03.11.2025

Click Here To Read/download The Order

Tags:    

Similar News