Development Authority Accepting Full One-Time Settlement Amount Estopped From Invoking Earlier Allotment Cancellation: Allahabad High Court
The Allahabad High Court has held that once a development authority accepts the entire amount calculated under its one-time settlement scheme without demur, it cannot thereafter fall back on an order cancelling the allotment passed years earlier. It held that the scheme is a binding contract between the parties and the authority is estopped by its own conduct from resiling from it.The bench...
The Allahabad High Court has held that once a development authority accepts the entire amount calculated under its one-time settlement scheme without demur, it cannot thereafter fall back on an order cancelling the allotment passed years earlier.
It held that the scheme is a binding contract between the parties and the authority is estopped by its own conduct from resiling from it.
The bench of Justice Siddhartha Varma and Justice Kunal Ravi Singh held,
“Once the amount demanded as per the OTS scheme is fulfilled, then by necessary legal fiction it is to be presumed that the Authority is satisfied that all the instalments, which were defaulted, have been paid as the acceptance of deposit was without any demur. Once that is the position then the cancellation order dated 19.06.2002 cannot survive as otherwise the entire purpose of the OTS scheme would fail to the detriment of the petitioner. The OTS scheme is a binding contract between the parties which entails legal consequences.”
A quarter in Barra-6, Kanpur Nagar was allotted to the petitioner's husband by the Kanpur Development Authority in 1992 at a cost of ₹40,648/-, a fourth payable at once and the balance in 120 instalments. He was put in possession, payments were made from time to time but not to schedule, and after his death in 2007 the petitioner continued to live in the quarter.
She later applied under the Authority's one-time settlement scheme and, told by a letter of 10 May 2013 that ₹76,187/- was payable either in two equal instalments by 29 June 2013 or in full within thirty days, paid the whole sum on 30 May 2013. Her application to have the quarter mutated in her name was met with the answer that the Authority's records showed the allotment cancelled on 19 June 2002, that no mutation could follow, and that she should take a refund.
Petitioner challenged the resulting orders of 28 August 2017 and 27 September 2017, pleading that the cancellation had never been served on her or her husband and that the Authority, having taken the settlement money, could not fall back on a cancellation eleven years old.
The Authority pleaded that the husband had defaulted repeatedly and had failed to pay the amount computed under an earlier settlement scheme of 2001, that both he and the petitioner knew of the cancellation, and that the allotment could now be restored only at current rates.
On service the Court found the counter affidavit silent. It noted that the Authority had annexed the Vice Chairman's approval but had nowhere stated when, by what mode or at what address the cancellation was served.
Relying on the Supreme Court's decision in Greater Mohali Area Development Authority and Others vs. Manju Jain and others, where it was held that an order not communicated to the party concerned creates no legal right enforceable in court and does not become effective until communicated, the Court held,
“Thus, we are of the considered view that as the order of cancellation was never communicated to the husband of the petitioner, the cancellation order is ineffective against the husband of the petitioner and the petitioner.”
On the settlement, the Court rejected, as fallacious, the contention that ₹76,187/- was only the first instalment and a further ₹38,093/- remained due, holding that the letter had put the whole defaulted amount at that figure. It observed that no shortfall had ever been communicated to her, and by accepting the application and the money the Authority had by its conduct accepted that it was not relying on the cancellation.
“The Authority by its conduct is now estopped from resiling from the settlement under the OTS scheme.”
Setting aside the cancellation order of 19 June 2002 along with the orders of 28 August 2017 and 27 September 2017, the Court partly allowed the writ petition and directed that the mutation application be decided in accordance with law within six weeks of production of a certified copy of the order, treating the entire amount as having been deposited.