Highest-Ranked Bidder Has No Vested Right To Govt Contract, Only Entitled To Fair Treatment: Allahabad High Court
The Allahabad High Court has held that a bidder in a public tender, even one treated as the highest bidder, has no rights beyond equality, fair treatment and negotiation, and that the bid he has offered cannot be enforced until it is translated into a formal contract. It held that so long as the competent authority has not passed an order finally accepting the bid, no vested right to a...
The Allahabad High Court has held that a bidder in a public tender, even one treated as the highest bidder, has no rights beyond equality, fair treatment and negotiation, and that the bid he has offered cannot be enforced until it is translated into a formal contract.
It held that so long as the competent authority has not passed an order finally accepting the bid, no vested right to a concluded contract arises.
The proposition was applied to a bidder who had become the lowest bidder by default, the technical bid of the declared L-1 having been found non-responsive after the work order was issued in its favour. The Court held that such a bidder gets only a right of negotiation, and having refused to execute the work at the L-1 rate, could not assail the cancellation of the tender that followed.
The bench of Justice Prakash Padia and Justice Indrajeet Shukla held,
“The highest bidder has limited rights of equality, fair treatment and negotiation; the bid offered by him cannot be enforced unless the same is translated into a formal contact, /agreement”
Petitioner, a firm that transports food grains as a contractor in the Department of Food and Civil Supply, Uttar Pradesh, bid for the carriage of food grains from godowns to fair price shops in Block Bansi and Block Uska Bazaar, District Siddharth Nagar, under a short-term e-tender notice dated 08.09.2026 issued by the Divisional Food Controller, Basti Division. It was the third round, earlier tenders for 35 and then 25 blocks having been cancelled at the technical bid stage for want of competition.
Three contractors bid. All three technical bids were found responsive on 14.09.2026 and the financial bids opened on 22.09.2026, on which M/s Hamara Pump Itwa Fuel Centre was declared L-1, the petitioner L-2 and M/s Om Traders L-3. The work order went to M/s Hamara Pump on 23.09.2026.
On a complaint that the vehicle offered by M/s Hamara Pump was registered as a tanker permitted to carry petroleum products and so did not answer the standard set by the tender notice, that work order was cancelled on 26.09.2026. M/s Hamara Pump never challenged the cancellation.
The Divisional Food Controller then asked the petitioner and M/s Om Traders to execute the work at the rate quoted by M/s Hamara Pump, consent to be furnished by 28.09.2026. The petitioner declined, contending that a non-responsive technical bid meant the financial bid of M/s Hamara Pump could not have been opened at all, so that his own bid had to be treated as L-1 at the rate he had quoted. M/s Om Traders too withheld consent. On 29.09.2026 the tender was cancelled and a fresh notice published.
Before the High Court, the petitioner contended that the technical bid of M/s Hamara Pump was ineligible from inception, leaving no occasion to open its financial bid, and that in a contract matter no party can be compelled to work at a price offered by a rival in the same bidding process. He added that the fresh notice carried letter no. 1386 and the cancellation order letter no. 1387, showing that the fresh notice had been directed before the earlier tender was cancelled, which reflected a prejudged and premeditated mind.
Counsel for the State submitted that the cancellation and the re-tendering rested on the Uttar Pradesh Procurement Manual, and that negotiation had been offered to the petitioner once the technical bid of M/s Hamara Pump was found non-responsive, but the petitioner had instead sought to force the authorities to accept his own price.
The petitioner also claimed parity with Block Nath Nagar, District Sant Kabir Nagar, where the L-1 bidder was found ineligible and the contract allotted to the L-2 bidder after negotiation. The Court held the claim misplaced, the two processes being entirely different: there the ineligibility was found before the work order was issued and the L-2 bidder consented to the L-1 rate and later to the scheduled rate, whereas in Block Bansi it surfaced after the work order and the petitioner refused consent.
“The law does not entitle any bidder/contractor to compel the other party to accept the rate offered by him unless a formal contract is entered into, thus, the petitioner has no legal or enforceable statutory right”
On the letter numbers, the Court held that both decisions had been taken on one and the same date, that the numbers appeared to have been interchanged and that the error was inadvertent, so that an allegation of bias founded merely on the serial numbers was devoid of merit. It nonetheless added,
“Though, the tender process requires fairness particularly when State is one of the parties, thus, the State Authorities are cautioned to be careful in future”
Taking note, on its own, of the decision of the Supreme Court in U.P. Avas Evam Vikas Parishad v. Om Prakash Sharma, which was cited by neither side, the Court held that even treating the petitioner as the highest bidder he had no right beyond equality and fair treatment in a transparent evaluation of competing bids free from any hidden agenda, and that until the competent authority finally accepted a bid no vested right to a concluded contract arose, regard being had also to Section 4 of the Indian Contract Act on when a communication is complete.
Turning to the petitioner's own position, the Court held,
“the L-2, i.e., the petitioner, was in de facto L-1 but notwithstanding highest bidder it does not get any indefeasible right to get the work order it has only the right of negotiation being a species of principles of natural justice, which was offered to the petitioner vide letter dated 26.09.2026, but the said opportunity to revise the rate was blatantly refused by the petitioner as he failed to furnish his consent to execute the work at the revised rate in terms of the proposal floated by the department”
Noting that no mala fide had been alleged against the department or made out from the record, and that the technical bids under the fresh notice had not been opened so that no right of the bidders in that process had crystallised, the Court held that the writ petition as framed must fail.
Counsel for the petitioner then stated, on instructions, that the petitioner was now willing to execute the contract at the rate quoted by M/s Hamara Pump, and counsel for the State said such consent would be honoured. The Court permitted the petitioner to file a fresh representation conveying his consent within one week, to be honoured by issuing the work order with all promptitude if there was no other legal impediment, and disposed of the writ petition.