The Jammu & Kashmir and Ladakh High Court has held that the statutory provision for deemed sanction of building permission cannot be invoked where the proposed construction does not conform to Master Plan norms and the concerned Development Authority has refused to grant a No Objection Certificate (NOC).

Dismissing a petition filed by residents of Pandach in Ganderbal, who claimed that their building permission stood automatically sanctioned because the authorities had failed to decide their application within the stipulated 60 days, Justice Sanjay Dhar observed that the deeming provision would not apply where the proposed construction violates planned development requirements.

The Court noted that the Srinagar Development Authority had declined to issue an NOC because the petitioners' building proposal did not conform to Master Plan norms. It held that once the Development Authority had withheld the requisite NOC, the petitioners could not claim that permission had been deemed to have been granted.

The Court also took note of the fact that the competent authority had specifically rejected the building permission application and communicated the decision to the petitioners on February 17, 2022.

Background

The petitioners, Ghulam Mohi-ud-Din Malik and others, approached the High Court seeking directions restraining the authorities from interfering with construction activities being undertaken on their land at Pandach, Tehsil Ganderbal.

According to the petitioners, they had applied for building permission in 2016. Their application was processed and NOCs were sought from various departments, including the Power Development Department and the Housing and Urban Development Department. Although the requisite NOCs were granted by certain departments, the petitioners claimed that they could not pursue the matter further due to the prevailing situation in the Valley.

They subsequently approached the authorities again after the situation improved following the COVID-19 pandemic, seeking consideration of their building permission application. However, according to them, no decision was taken.

The petitioners contended that under Section 247 of the Municipal Corporation Act and the J&K Unified Building Bye-Laws, the authorities were required to decide their application within 60 days. Since no decision had been communicated within that period, they claimed that the building permission stood deemed to have been sanctioned by operation of law.

Proceeding on that understanding, they collected construction material at the site but alleged that the authorities obstructed their construction activities despite the deemed sanction.

During the proceedings, the High Court had directed the respondents to take a decision on the petitioners' building permission application. As the authorities did not initially comply, the petitioners instituted contempt proceedings.

In their compliance report, the respondents informed the Court that the petitioners' building permission case had been processed in 2016 through application No.3732 dated March 29, 2016, for construction of a ground-plus-three-storey guest house with stilt parking on the ground floor.

However, the Srinagar Development Authority had refused to issue an NOC on the ground that the drawings and proposal submitted by the petitioners did not conform to Master Plan norms. The respondents further stated that the competent authority had rejected the building permission application and issued a communication dated February 17, 2022, conveying the rejection to the petitioners.

The respondents also submitted that, pursuant to an interim order dated April 26, 2023, the petitioners were required to submit a fresh application through the online portal. According to them, no such application had initially been filed.

The petitioners, however, filed a response stating that they had submitted a fresh online application for building permission on August 1, 2025.

Court's Observation

Justice Dhar noted that the petitioners' principal contention rested on the assertion that the authorities had failed to decide their 2016 application within 60 days and, therefore, permission was deemed to have been granted under Section 247 of the Municipal Corporation Act and the relevant provisions of the J&K Unified Building Bye-Laws.

The Court, however, pointed out that the petitioners themselves had acknowledged in their writ petition that deemed building permission was subject to several conditions.

These included compliance with planned development requirements, zoning regulations under the Master Plan, land-use restrictions, Floor Area Ratio (FAR), setback norms, Green Belt alignment and the rights of adjacent plot holders. The title to the land was also required to be free from dispute.

Examining the respondents' compliance report, the Court found that the Srinagar Development Authority had refused to issue the requisite NOC because the petitioners' drawings and construction proposal did not conform to Master Plan norms.

The Court held that the statutory provision relating to deemed sanction could not be invoked in such circumstances.

“Once the development authority has not furnished the NOC, the provision with regard to deemed sanction of building permission would not get attracted,” Justice Dhar observed.

The Court further clarified that deemed sanction would not operate where the proposed construction violates planned development requirements envisaged by the concerned authorities, including Development Authorities.

It held that the refusal of the Srinagar Development Authority to grant the NOC was sufficient to prevent the petitioners from claiming deemed approval of their building permission application.

The Court also took note of the respondents' specific submission that the competent authority had rejected the petitioners' application and communicated the decision through a letter dated February 17, 2022.

In view of the specific rejection, the petitioners could not contend that their building permission had automatically been sanctioned merely because the authorities had allegedly failed to act within the stipulated period.

The Court, therefore, found no legal basis to accept the petitioners' claim of deemed building permission.

Finding no merit in the writ petition, the High Court dismissed the same.