FCI Cannot Impose Unilateral Penalty On Godown Owner Through Administrative Decision: J&K&L High Court Quashes Recovery Notices
The Jammu & Kashmir and Ladakh High Court has held that the Food Corporation of India (FCI) cannot unilaterally impose financial penalties or alter the agreed hiring arrangement with a private godown owner by relying on decisions of an internal High Level Committee, when the underlying Lease and Service Agreement does not authorise such recoveries.
Setting aside the dismissal of a writ petition filed by M/s Alpine Agro Services, a Division Bench comprising Justice Sanjeev Kumar and Justice Mohd. Yousuf Wani held that an administrative decision, even if intended to ensure uniformity in the treatment of contractors, cannot automatically become part of an existing contract or create additional financial liabilities without the consent of the contracting parties.
The Court clarified that although the appellant had breached its undertaking to complete the black-topping of the internal roads within the stipulated period, that default did not, by itself, empower the FCI to impose a monetary penalty or convert the agreed Guaranteed Hiring Basis into Actual Utilization Basis.
The Bench observed,
“In the absence of any specific clause in the terms and conditions of the Lease and Service Agreement executed between the appellant and the respondent-Corporation, the respondent-Corporation could not have unilaterally imposed a penalty, that too on the basis of calculations made at its own level.”
Allowing the intra-court appeal, the High Court quashed the impugned recovery notices and directed the FCI to release any outstanding rentals payable to the appellant, preferably within two months.
Background
The dispute arose from a contract awarded to M/s Alpine Agro Services under the Private Entrepreneur Guarantee Scheme for construction and operation of a godown with a storage capacity of 17,500 metric tonnes at Shilvat. The FCI took over the facility on a Guaranteed Hiring Basis from February 2015.
The appellant had undertaken to complete the drainage work by March 2015 and the black-topping of internal roads by September 2015. The deadline for black-topping was subsequently extended until February 26, 2016. However, the work remained incomplete beyond that date and was ultimately completed during May June 2017.
The FCI initially recovered ₹1,58,002 from the appellant through an office order dated January 17, 2018, on account of the delay. It subsequently issued further recovery communications dated September 3, 2021, and November 15, 2021, implementing decisions of its High Level Committee concerning regulation of hiring charges and deductions on the basis of estimated cost savings.
Challenging the additional recoveries, the appellant contended that the Lease and Service Agreement contained no provision authorising the FCI to impose such penalties or unilaterally alter the agreed hiring arrangement.
A Single Judge dismissed the writ petition on June 6, 2026, holding that the appellant had failed to fulfil an essential contractual obligation despite an extension of time. The firm thereafter approached the Division Bench.
Court's Observation
The Division Bench framed the central issue as whether the FCI could recover additional amounts from the appellant for delayed completion of the black-topping work on the basis of decisions taken by its High Level Committee.
At the outset, the Court acknowledged that the appellant had failed to complete the work within the stipulated period, even after being granted an extension. It rejected the argument that the Corporation's decision to take over and utilise the godown had absolved the appellant of its contractual obligation.
However, the Bench drew a distinction between the existence of a contractual breach and the authority to impose a particular financial consequence for that breach.
“However, such failure, by itself, would not authorise the respondents to impose financial liability without any contractual or legal basis,” the Court observed.
The Bench held that the rights and liabilities of the parties were governed by the Lease and Service Agreement. Although the High Level Committee had formulated a uniform policy to regulate hiring charges in cases involving non-completion of black-topping work by PEG investors, its decisions could not automatically be incorporated into contracts already executed.
The Court observed,
“The decisions of the High Level Committee, even if intended to ensure uniformity in the matter of hiring charges payable to PEG investors, cannot automatically become part of an existing contract. Unless the agreement permits such a change or the parties have agreed to it, an administrative decision cannot, by itself, create additional financial liabilities.”
Examining the agreement, the Bench found that there was no clause empowering the FCI or its High Level Committee to unilaterally alter the contractual terms or impose the additional recoveries in question.
The Court also noted that Clauses 4 and 5 of the Lease and Service Agreement provided a mechanism for dealing with deficiencies or breaches. The Corporation could have invoked those provisions and, if it considered the failure serious enough, proceeded to terminate the agreement. Alternatively, it could have undertaken the necessary work itself and recovered the actual expenditure from the rentals payable to the appellant.
However, the FCI had taken over the godown, put it to use and continued to utilise it without demonstrating that the absence of a black-topped road had caused any financial loss or prevented optimum utilisation of the facility.
The Bench observed that the Corporation had consciously allowed the appellant additional time to complete the work and had thereafter executed a fresh Lease and Service Agreement without incorporating any additional stipulation concerning the delayed black-topping.
“The respondent-Corporation took over possession of the godown and put it to use without suffering a loss of even a penny,” the Court noted, adding that there was no pleaded case of any financial loss arising from the delayed work.
The Court then examined the earlier recovery of ₹1,58,002 imposed through the office order dated January 17, 2018. It noted that the FCI had sought to explain that the earlier amount was recovered pursuant to audit objections raised by the Comptroller and Auditor General, whereas the subsequent recoveries were based on the High Level Committee's policy concerning Actual Utilization Basis and deductions equivalent to twice the Cost Saving Amount.
The Bench, however, found that the earlier recovery itself was not in consonance with the Lease Agreement, as it had also been calculated and imposed unilaterally.
Importantly, the Court held that the earlier recovery was a one-time penalty for delayed black-topping and should have brought the issue to a close.
“From a reading of order dated 17.01.2018, it is abundantly clear that this was a one-time penalty imposed for delayed black-topping of the road and, therefore, should have been treated to have put a quietus on the issue,” the Bench observed.
It further held that even this recovery could not have been imposed without associating the appellant in the process of calculating or determining the penalty, particularly when the agreement contained no specific clause prescribing the imposition or mode of calculation of damages or penalty.
The FCI had also sought to justify the recoveries on the ground that the appellant had saved the cost of black-topping the road while continuing to receive the full contractual rentals. It argued that allowing the appellant to retain this benefit would amount to unjust enrichment.
The Bench examined this contention with reference to Section 70 of the Indian Contract Act, 1872, which deals with the obligation of a person enjoying the benefit of a non-gratuitous act.
The Court explained that the doctrine requires three essential conditions: a person must lawfully do something for another or deliver something to that person; the act or delivery must not be intended to be gratuitous; and the other person must enjoy its benefit.
Applying these requirements, the Bench held that the FCI had not lawfully delivered any benefit to the appellant outside the contractual arrangement. The rentals had been paid in consideration of the Corporation's utilisation of the godown under the agreed terms.
The Court also noted that the FCI had continued to use the facility without suffering any financial loss on account of the unfinished road and had not invoked the contractual mechanism available to it for completing the work and recovering the actual expenditure.
It consequently held,
“The doctrine of unjust enrichment invoked by the respondent-Corporation is not attracted to the facts and circumstances of the case.”
The Bench further pointed out that the appellant's failure to complete the black-topping work had not caused any loss or damage to the Corporation, at least none had been pleaded or established before the writ Court or the appellate Bench.
Referring to Sections 73 and 74 of the Contract Act, the Court explained that compensation for breach of contract must be founded on the applicable statutory and contractual requirements. Section 73 permits compensation for loss or damage caused by the breach, while Section 74 concerns reasonable compensation where the contract stipulates a sum payable or contains a penalty clause.
In the present case, the agreement contained no clause specifying a sum payable by the appellant for the breach in question or prescribing a penalty.
The Court held that the Corporation could not rely upon a general administrative decision to create a financial liability which had no foundation in the contract.
“Neither the respondent-Corporation, nor the High Level Committee constituted by it had the mandate of altering, superseding or adding to the terms and conditions of the Lease Agreement, that too unilaterally and without the consent of the appellant,” the Bench held.
The Court added that the High Level Committee's decision could form the basis of future Lease and Service Agreements, but could not be retrospectively incorporated into the existing agreement with Alpine Agro Services.
It also rejected the argument that the appellant's failure to separately challenge the general decision of the High Level Committee rendered its writ petition liable to dismissal. The challenge was directed against the recovery notices, which the Court found to be unauthorised under the governing contract.
Holding that the FCI had no contractual authority to impose the impugned financial recoveries or convert the agreed Guaranteed Hiring arrangement into Actual Utilization charges, the Division Bench allowed the appeal. The Court set aside the Single Judge's judgment, allowed the original writ petition and quashed the recovery notices.