The Supreme Court has appointed former judge Justice Sanjay Karol as chairperson of a reconstituted Special Committee to resolve competing claims over plots in the Okhla Enclave project in Faridabad, Haryana. 

A bench of Justice Vikram Nath and Justice Sandeep Mehta passed the order in a batch of applications arising from the long-pending dispute concerning the residential project in Faridabad, while also granting claimants who failed to submit their documents earlier a final three-week opportunity to do so.

Justice Karol replaces former Supreme Court judge Justice Vikramajit Sen, who resigned as Committee chairperson after concerns arose over local Town and Country Planning Department (DTCP) officials sanctioning building plans for 480 claimants whose title documents had not been verified.

Describing the dispute as one involving several competing claims and administrative irregularities, the Court observed that “the factual matrix of the present dispute has been complicated beyond imagination by a multiplicity of judicial and administrative proceedings spanning nearly four decades, overlapping categories of claimants, and glaring discrepancies in the numerical data emerging across various records.”

The project, spread over approximately 235 acres, has been embroiled in litigation over alleged unauthorised and duplicate allotments, incomplete development work and competing claims to plots. The Court noted that 2,036 claims had been received for Phase II scrutiny, including 1,637 supported by registered sale deeds, 102 by powers of attorney and 297 by other documents. Preliminary checks had revealed duplicate sale deeds relating to identical plots.

The Court also highlighted the acute shortage of available land. Although 1,011 allottees had already been found eligible in Phase I, only around 150 vacant plots were reportedly available against 866 verified No Profit No Loss (NPNL) allottees. Similarly, 49 verified General Category allottees were competing for just one vacant plot. The Court noted that “the physical handing of possession is stalled owing to severe physical inventory deficit.”

The Court clarified that the entitlements of the 1,011 verified allottees, identified by the earlier Committee and accepted by the Court in July 2023, stand judicially confirmed. However, the remaining claims require detailed scrutiny.

It directed claimants who had not submitted their complete documents to place their applications before the State's Nodal Officer within three weeks from November 20. The Nodal Officer will index the applications and forward them to the Committee. Any allotment in favour of these applicants will remain subject to the Supreme Court's final orders.

The Court further clarified that members of the Okhla Enclave Plot Holders (Allottees) Forum cannot claim automatic exemption from verification and must also submit their documents for scrutiny. General Category purchasers who acquired plots in the open market will have their claims examined individually, without applying the restriction of one plot per family.

The reconstituted Committee has been tasked with verifying pending title documents, identifying duplicate or fraudulent claims, assessing the actual availability of land and formulating an equitable allocation scheme. It will also investigate the alleged irregular sanctioning of building plans for unverified claimants and examine the financial liabilities of the developer and the allottees.

The Committee will further consider whether unused land earmarked for the EWS category can be reconfigured into NPNL-sized plots or multi-storeyed residential complexes to address the shortage, subject to the applicable legal and planning framework.

The broad parameters, terms of reference, and supervisory mandate governing the functioning of the reconstituted Special Committee shall be as under: -

"a. Undertake a comprehensive document scrutiny, revenue audit, and title verification of all pending Phase II claims, including applications received within the final 3-week window granted herein. Scrutiny shall be conducted with strict adherence to the twin cut-off parameters as affirmed vide judgment dated 3rd October, 2019. The Special Committee may examine the corresponding revenue records to resolve title anomalies, including duplicate sale deeds and parallel third-party transfers, and weed out fraudulent claims.

b. Audit the physical status of the 1,011 verified claimants whose basic entitlement stands crystallized vide order dated 11th July, 2023; ascertain how many of them have secured physical possession, how many remain unaccommodated due to inventory deficits, and identify all unauthorized occupants or encroachers currently holding project land.

c. Evaluate the net unencumbered plottable land vis-à-vis verified allottees and formulate a transparent, equitable allocation scheme, incorporating draws of lots, layout plan modifications, or monetary refund with/without interest, to address the acute plot deficit. In doing so, the Special Committee shall examine whether the DTCP can be directed to re-layout, rezone, or convert unutilized EWS land banks, if any, into NPNL-sized plots or multi-storey residential group housing complexes to maximize yield and mitigate physical land shortfalls.

d. Prepare and place before this Court final category-wise lists of verified allottees across NPNL, EWS, and General categories, as well as eligible commercial shop plot claimants who satisfy prescribed eligibility norms.

e. The Special Committee shall investigate and report on the administrative irregularities highlighted in the communication addressed by Justice (Retd.) Vikramajit Sen regarding building plans sanctioned by local DTCP officials in favour of unscrutinised claimants up to 25th March, 2025, in direct breach of this Court's restraint orders, and suggest appropriate remedial and disciplinary measures.

f. The Special Committee shall verify the exact financial liabilities of both the developer and the verified allottees, determine the amounts actually paid till date, and suggest effective recovery mechanisms to secure project development funds.

g. The Special Committee shall have full autonomy to frame such ancillary issues as it may deem fit, and to lay down its own procedure and modalities for conducting the scrutiny exercise in an expeditious and transparent manner."

The State of Haryana has been directed to provide the Committee with the relevant records and necessary administrative, logistical and financial support.