Delay Compensation Should Be Given In Addition To Already Pre-existing Compensation In Builder- Buyer Agreements: NCDRC
Ayushi Rani
4 Sept 2024 12:15 PM IST

Next Story
4 Sept 2024 12:15 PM IST
The National Consumer Disputes Redressal Commission, presided by Dr Inder Jit Singh, held Raheja Developers liable for deficiency in service. It was held that delay compensation at 6% per annum should be given in addition to any compensation already outlined in the Builder-Buyer Agreement. Brief Facts of the Case The complaint was filed jointly by 11 complainants who booked units...