INS Vindhyagiri - MV Nordlake Collision | Liability Can Be Limited At Interim Stage Before Completion Of Trial: Bombay High Court

Amisha Shrivastava

22 Feb 2023 7:30 PM IST

  • INS Vindhyagiri - MV Nordlake Collision | Liability Can Be Limited At Interim Stage Before Completion Of Trial: Bombay High Court

    Ruling that the liability of a vessel owner for an accident can be limited at the interim stage before the completion of the trial, the Bombay High Court limited the liability of German company M.V. Nordlake Gmbh for the 2011 MV Nordlake – INS Vindhyagiri collision in Mumbai.“Once the suit is instituted, it is not imperative that the order to limit liability can only be after a full...