The Haryana Real Estate Appellate Tribunal Dismisses The Claim Of The Builder Based On The 'Force Majeure' Clause

Aryan Raj

2 Feb 2024 12:00 PM GMT

  • The Haryana Real Estate Appellate Tribunal Dismisses The Claim Of The Builder Based On The Force Majeure Clause

    In its recent decision, the Haryana Real Estate Appellate Tribunal (HREAT or the Tribunal) comprising Justice Rajan Gupta (Chairman) and Anil Kumar Gupta (Technical Member) rejected the appellant's (“Promoter”) claim based on the “Force Majeure” clause. The Tribunal ruled that the COVID-19 pandemic occurred after the date by which the allottees were supposed to receive possession...

    In its recent decision, the Haryana Real Estate Appellate Tribunal (HREAT or the Tribunal) comprising Justice Rajan Gupta (Chairman) and Anil Kumar Gupta (Technical Member) rejected the appellant's (“Promoter”) claim based on the “Force Majeure” clause. The Tribunal ruled that the COVID-19 pandemic occurred after the date by which the allottees were supposed to receive possession of the flat.

    Facts and Background

    Respondent (“Allotees”) in this case purchased a unit in the “Cosmos Express 99” project located in Gurugram. The Allottees were supposed to receive the possession of the flat by 27.06.2017. However, there was a notable delay of three years, four months, and twenty-two days in the handover of possession.

    In response to the promoter's delay in delivering possession, the complainant lodged a formal complaint with the Gurugram Authority in 2019. The primary prayer was to grant possession and impose delay possession charges (DPC).

    The Authority ruled in favour of the Allottee, instructing the Promoter to pay interest at the prescribed rate of 9.30% per annum for each month of delay.

    Aggrieved with the Authority's order, the appellant (promoter) filed an appeal before this Tribunal, invoking Section 43(5) of the Real Estate (Regulation and Development) Act, 2016.

    Section 43 of Real Estate (Regulation and Development) Act : Establishment of Real Estate Appellate Tribunal

    (5) " Any person aggrieved by any direction or decision, or order made by the Authority or by an adjudicating officer under this Act may prefer an appeal before the Appellate Tribunal having jurisdiction over the matter”.

    Submission by Appellant

    The delay in the handling over the possession occurred due to force majeure conditions prevailing due to onset of covid-19 pandemic. Authority's calculation of interest at 9.30% per annum is erroneous and incorrect and, the Appellant was not given ample opportunity to present their case before the Authority.

    Submission by Respondent

    That the ample opportunity was granted to the appellant-promoter to appear before the Authority for reply to the complaint and for the purpose of rebuttal.

    Despite opportunities, the appellant-promoter failed to appear before the Authority. Appellant-Promoter was always aware of the pendency of the matter before the Authority.

    Also, no such benefit of “Force Majeure” can be claimed by the Appellant as per the law.

    REAT Verdict

    Tribunal on the defence of “Force Majeure” used by Appellant-Promoter noted that the scheduled possession date for the unit as per the agreement was 27th June 2017, whereas the Govt of India acknowledged the spread of the Covid-19 pandemic in March 2020, well after the deemed date of delivery of the unit.

    Tribunal also noted that the appellant-promoter has not provided the details regarding the construction stage at the time of spread of the pandemic and its impact on the project's progress. Also, the appellant has not substantiated its claim with supporting evidence, failing to demonstrate how force majeure conditions due to the Covid-19 pandemic, even if they occurred, significantly impeded the project's progress.

    Tribunal held that "we are not inclined to grant relief to the appellant-promoter based on the

    alleged delay due to force majeure caused by the Covid-19 pandemic."

    Tribunal also observed that the Authority had issued notice of the complaint to the respondent-promoter (in this case "appellant") by speed post as well as through email. Despite communication, respondent-promoter failed to appear and file reply to the complaint. The Authority, thus, proceeded to decide the complaint ex-parte.

    Tribunal further noted that the notice (issued on 08.01.2020) explicitly stated that if the appellant-promoter fails to respond within the specified timeframe, their defence would be liable to be struck off, and the proceedings would be ex-parte.

    The Tribunal also addressed the appellant's concern, emphasizing that the interest granted by the Authority had been incorrectly and erroneously calculated at 9.30%, deviating from the highest Marginal Cost of Funds-Based Lending Rate (MCLR) offered by the State Bank of India (SBI) on the date of the Authority's order.

    Upon examining the interest award by the Authority, the Tribunal referred to the SBI's highest MCLR prevailing on the date of order, which was 7.30% . The Authority, in accordance with Rule 15 of the Haryana Real Estate (Regulation and Development) Rules, 2017, incorporated an additional 2%, resulting in an awarded interest rate of 9.3% per annum. After a thorough examination of Rule 15, the Tribunal affirmed the interest rate determined by the Authority.

    Rule 15 of Haryana Real Estate (Regulation and Development) Rules: Interest Payable by Promoter and Allottee

    “ An allottee shall be compensated by the promoter for loss or damage sustained due to the promoter failure to give possession of the apartment/ plot in accordance with terms and conditions of agreement. The promoter shall return the entire amount with interest as well as the compensation payable. The rate of interest payable by the promoter to the allottee shall be the State Bank of India highest marginal cost of lending rate plus two percent.”

    Case:( M/s Cosmos Infra Engineering India Pvt. Ltd vs Abhinav Kohli)

    Case No: Appeal No. 418 of 2021

    Counsel for appellant: Mr. Rishab Bajaj, Advocate

    Counsel for Respondent: Mr. Narender Pal Bhardwaj, Advocate

    Click Here To Read/Download Order


    Next Story