Contractor Claiming Loss Of Profits Due To Delayed Execution Must Prove That Other Works Were Lost Due To Delay : Supreme Court

Pallavi Mishra

28 Sept 2023 10:51 AM IST

  • Contractor Claiming Loss Of Profits Due To Delayed Execution Must Prove That Other Works Were Lost Due To Delay : Supreme Court

    The Supreme Court Bench comprising Justice Sanjiv Khanna and Justice M.M. Sundresh, has held that in arbitral proceedings where the execution of a contract is delayed and the Contractor claims loss arising from depletion of income, then the Contractor must prove that there was alternative work available for him/her by placing on record invitation to tender, which were rejected by the...