The Delhi High Court bench of Justice Ravinder Dudeja has held that the grant of post-award interest under Section 31(7)(b) of the Arbitration and Conciliation Act, 1996 (“the Act”) is mandatory. The only discretion which the Arbitral Tribunal has is to decide the rate of interest to be awarded. Where the Arbitrator does not fix any rate of interest, then statutory rate, as...