The National Consumer Disputes Redressal Commission, presided by Dr. Inder Jit Singh, held that builders cannot demand interest from the buyer if the project is already delayed beyond the agreed-upon time. The Commission held the builder liable for deficiency in service for charging interest from the buyer upon an already delayed project. Brief Facts of the Case ...