Builder Cannot Demand Interest For Delayed Projects: NCDRC Holds Puri Construction Liable For Deficiency In Service
Ayushi Rani
12 Jun 2024 7:30 PM IST

Next Story
12 Jun 2024 7:30 PM IST
The National Consumer Disputes Redressal Commission, presided by Dr. Inder Jit Singh, held that builders cannot demand interest from the buyer if the project is already delayed beyond the agreed-upon time. The Commission held the builder liable for deficiency in service for charging interest from the buyer upon an already delayed project. Brief Facts of the Case ...