The Delhi State Consumer Disputes Redressal Commission bench comprising Justice Sangita Dhingra Sehgal (President) and Ms. Pinki (Member) stated that when dealing with builder services lacking a defined timeframe, a reasonable duration for fulfilling the contract under the Indian Contract Act 1872 falls within 24 to 48 months. The bench further argues that the complainants cannot...