Evidence Needs to Be Provided To Cite Force Majure Clauses As Reason Of Delay: Delhi State Commission Holds Assotech Moonshine Liable For Deficiency

Ayushi Rani

30 Jun 2024 3:15 PM IST

  • Evidence Needs to Be Provided To Cite Force Majure Clauses As Reason Of Delay: Delhi State Commission Holds Assotech Moonshine Liable For Deficiency

    The Delhi State Commission, presided by Justice Sangita Dhingra Sehgal and J.P. Agrawal, held Asootech Moonshine Developers liable for deficiency in service due to delay in handing over possession citing force Majure clause. Furthermore, it was held that the developer needs to provide substantiating evidence to show that Force Majeure conditions caused the delay. Brief Facts of the Case...