Karnataka RERA Directs Builder To Refund Homebuyer's Amount With Interest After Builder Failed To Complete Project On Time

Aryan Raj

2 May 2024 1:00 PM IST

  • Karnataka RERA Directs Builder To Refund Homebuyers Amount With Interest After Builder Failed To Complete Project On Time

    Karnataka Real Estate Regulatory Authority (Authority) bench, Comprising of Justice HC Kishore Chandra (Chairman) has directed builder to refund the homebuyer's amount with interest after builder failed to deliver the possession of the flat on promised timeframe. Background Fact The homebuyer (complainant) booked a flat in the builder's project named Mantri Manyat Energia. Both...