MahaRERA Rejects Complaint Against Piramal Builders, Rules Builder Cannot Be Held Responsible For Homebuyer's Delayed Home Loan Approval

Aryan Raj

4 Nov 2025 9:10 AM IST

  • MahaRERA Rejects Complaint Against Piramal Builders, Rules Builder Cannot Be Held Responsible For Homebuyers Delayed Home Loan Approval

    Maharashtra Real Estate Regulatory Authority (“Authority”) bench comprising Mahesh Pathak (Member I), held that Piramal Estate is not liable for the Homebuyer's delayed home loan approval as the project was already registered with MahaRERA and all relevant information, including pending litigations was publicly available. Homebuyer had alleged that his home loan was...