The State cannot cite delay in approaching the court to absolve itself of its responsibility towards those whose private property has been “expropriated” or taken for public use without compensation, the Bombay High Court has held. It ruled in favour of urban landowners who approached the court in 2021, nearly four decades after an electricity sub-station was built on their land.A...