The Bombay High Court recently rejected the Mumbai Metro One Private Limited's (MMOPL) request to have its dispute with Hindustan Construction Company (HCC) resolved by way of arbitration. The Court deciding that the arbitration clause in the original contract no longer applies to new issues emerging from the settlement, ruled that once a "full and final" settlement agreement is executed,...