Land Reservation Lapses If No Acquisition Steps Taken Within 24 Months Of Purchase Notice Under MRTP Act: Bombay High Court
Saksham Vaishya
20 Feb 2026 4:05 PM IST

Next Story
20 Feb 2026 4:05 PM IST
The Bombay High Court has held that if no steps are commenced for the acquisition of land after the expiry of the stipulated period under Section 127(1) of the Maharashtra Regional and Town Planning Act, 1966, the land is deemed to be released from such reservation, allotment or designation. The Court observed that once a valid purchase notice is served and the Planning Authority fails to...