Mere Interest In Project Does Not Justify Impleadment Of Non-Signatory In Arbitration Without Contractual Participation: HP High Court

Mohd Malik Chauhan

1 Jan 2026 5:55 PM IST

  • Mere Interest In Project Does Not Justify Impleadment Of Non-Signatory In Arbitration Without Contractual Participation: HP High Court

    The Himachal Pradesh High Court dismissed a writ petition holding that mere financial or consequential interest was insufficient to implead a non-signatory in the arbitration proceedings unless the stringent tests as laid down by the Supreme Court which include participation in the negotiation, performance or termination of contract were satisfied. Justice Ajay Mohan Goel...

    Next Story