Holding that debarment is never permanent and its duration must depend upon the gravity of the misconduct, the Jammu and Kashmir and Ladakh High Court has ruled that even where a contractor is found guilty of forgery and financial impropriety, punitive action cannot be allowed to operate endlessly. The Court underscored that penalties in contractual matters must remain proportionate,...