Release Of Bank Guarantee Is Admission Of Unblemished Completion Of Work: Jharkhand High Court Directs Payment Of Contractor's Dues
Rushil Batra
16 July 2026 6:00 PM IST
The Jharkhand High Court has held that release of a performance bank guarantee by the employer amounts to an admission by conduct that the contractor has completed the work and all post-execution obligations to the employer's satisfaction. Holding that the respondents could no longer dispute the quality or completion of the work after releasing the bank guarantee, the Court directed the...