For EC Exemption, NHAI Contractor Must Show Work Is Exclusively For Linear Project Based On Pre-2024 Contract: Kerala High Court

Anamika MJ

23 Aug 2025 2:56 PM IST

  • For EC Exemption, NHAI Contractor Must Show Work Is Exclusively For Linear Project Based On Pre-2024 Contract: Kerala High Court

    The Kerala High Court held that contractors executing National Highway projects cannot claim automatic exemption from environmental clearance (EC) requirements merely because they hold a work order from the National Highways Authority of India (NHAI). They have to show that they are holding a work order executed before March 21, 2024, and that they are doing the work exclusively for the...