Allottee Not Responsible If Delay In Construction Is Due To Procedural Requirements, Punjab & Haryana HC Quashes ₹94 Cr Extension Fees By HUDA
Aiman J. Chishti
30 April 2025 3:35 PM IST

Next Story
30 April 2025 3:35 PM IST
The Punjab & Haryana High Court has quashed the extension fees of Rs. 93.12 Crore imposed on a government organisation by the Haryana Urban Development Authority (HUDA) for delay in construction of flats for government employee on land allotted in 1996.The Court found that the delay in construction was due to procedural and administrative requirements, hence the delay period will...