State Bodies Can't Invoke Public Interest To Deny Payment For Services Already Availed At Approved Rates: Telangana High Court

  • State Bodies Cant Invoke Public Interest To Deny Payment For Services Already Availed At Approved Rates: Telangana High Court

    The Telangana High Court pulled up the Food Corporation of India (FCI) for withholding payment of admitted dues to a Handling and Transport (H&T) contractor, holding that FCI after choosing to accept the contractor's rates cannot claim public interest to avoid payment. The single judge bench of Justice Nagesh Bheemapaka, allowed a plea filed by Sri Venkata Ramana Lorry Transport,...

    The Telangana High Court pulled up the Food Corporation of India (FCI) for withholding payment of admitted dues to a Handling and Transport (H&T) contractor, holding that FCI after choosing to accept the contractor's rates cannot claim public interest to avoid payment. 

    The single judge bench of Justice Nagesh Bheemapaka, allowed a plea filed by Sri Venkata Ramana Lorry Transport, directing the respondent FCI to settle the outstanding bills of Rs 91 lakhs within six weeks, payable to  Telangana State Warehousing Corporation (TSWC) initially, who in turn should settle the dues with the petitioner-company within 2 weeks, while holding that the refusal to pay was not justified.

    To recap, the FCI, before the High Court, argued that the rates quoted by the petitioner-company were higher than those of nearby warehouses, and that paying them would cause a loss to the public exchequer. It contended that it had only concurred with the rates in the initial phase of discussion with TSWC, and not thereafter.

    However, the court found this stand as untenable. The single judge bench noted that the FCI had full knowledge of the tender process, and had actively participated by approving the rates. Furthermore, the court pointed out that the petitioner had been performing the work without FCI's protest for over two years, and that the FCI could not retroactively refuse to pay for services availed.

    “…This Court is mindful of the role of the FCI under the National Food Security Act, 2013 and the need for care in spending public money. But public interest is also served when public bodies honour their word and pay for what they have received. The FCI was free to reject the rates and make its own arrangements, and was told so. Having chosen to accept both the rates and the services, it cannot raise public interest after the work is over to avoid paying….”, the court underscored in its order.

    Hence, the court rejected the FCI's primary objection that the writ petition was not maintainable due to the absence of privity of contract, citing the apex court orders in ABL International Ltd. v. Export Credit Guarantee Corporation of India Ltd [2003] and Unitech Limited v. TSIIC [2021].

    “….The FCI's plea of no privity does not help it. The godowns were hired by the FCI. The stocks handled were the FCI's. Under Clause XVI of the tender conditions, the contractor's bills are scrutinised and accepted by the depositor and paid out of the depositor's money. The Warehousing Corporation sought the FCI's concurrence, and the FCI gave it …The FCI had a direct and deciding role and it is the FCI which is holding back the money. Having taken the benefit of the services, it cannot rely on the absence of a direct contract to avoid paying at rates it accepted. In any case, its duty to act fairly comes from Article 14 and not from the contract alone…”, the court underscored

    For context, the petitioner-transport company was appointed as the H&T contractor for the Agricultural Market Committee (AMC) godowns at Chelgal and Metpally in June 2020. The contract was for a period of two years, extendable by six months, to handle stocks stored by the FCI and the Telangana State Civil Supplies Corporation.

    While the Civil Supplies Corporation approved the rates and settled the bills promptly, the FCI refused to do so. Although the FCI's Regional General Manager concurred with the tendered rates on July 12, 2021 vide a letter, wherein it agreed to pay 525% ASOR for handling and Rs. 115/MT for transportation at Chelgal, and 575% ASOR and Rs. 245/MT at Metpally, the actual payment was never released.

    The petitioner company had completed the work until November 2022, and the unpaid bills came to the tune of Rs 91 lakhs.

    When the petitioner approached the High Court earlier, the respondents were directed to pass a reasoned order. Subsequently, the TSWC passed an order stating it could not pay the petitioner until the FCI released funds in their favour, whereas the FCI passed an order on July 22, 2024, refusing to pay the tendered rates.

    After hearing all the concerned parties, the court also highlighted that TSWC, which floated the tender and signed the agreement, could not let go of its responsibility, by claiming it was merely an agent of the FCI. Clause XVI(a) of the Tender Schedule, which made payment conditional on receipt from depositors, could not be used as a shield to deny payment for work admittedly done, the court added.

    “….The action of the respondents in withholding the payment for more than a year, despite the petitioner having completed the work to their satisfaction, is violative of Article 14 of the Constitution of India…”, the court observed.

    The court relied on the Supreme Court's decision in M/s Surya Constructions v. State of Uttar Pradesh[2019], wherein it was held that where the amount due is not in dispute, a writ petition cannot be dismissed, merely because the claim arises out of a contract.

    About the defence of alleged clarification sought by FCI from TSWC on its 'dual procedure' along with 'initial concurrence' regarding the tender terms, the court noted as below:

    “…The FCI now …points to another letter of the same number and date, 12.07.2021, addressed to the Managing Director of the Warehousing Corporation, asking for clarification about its "dual procedure". That letter is a general query. It notes that the Warehousing Corporation applies nearby own depot rates at some AMC and MARKFED godowns while tendering at others, including AMC Chelgal and AMC Metpally, and asks why. It says nothing about withdrawing or holding back the 29 concurrence given the same day for these two godowns..”, the court pointed out.

    The court noted that the aforesaid letter came along with the concurrence letter, essentially raising a 'policy question' for the future alone.

    “…the only sensible reading is that the FCI approved the rates for these two godowns while separately raising a policy question for the future. Whether or not that question was answered, it could not cancel a specific approval under which work went on for more than a year afterwards…”, the court clarified further.

    Accordingly, the court quashed the orders dated September 5, 2024, and July 22, 2024, issued by the TSWC and FCI, respectively and directed the respondents to release the outstanding amount along with interest.

    Sebin James

    Sebin James is a Correspondent with LiveLaw, covering the Telangana High Court