The Chhattisgarh High Court recently directed the National Thermal Power Corporation [NTPC] to try and amicably resolve a contractual dispute before proceeding to invoke the bank guarantee furnished by its contracting party. Restraining the statutory corporation from encashing the bank guarantee, if not done yet, Justice P. Sam Koshy observed,"Considering the fact that the bank...