[Arbitration & Conciliation Act] Proceedings U/S 9 Interim In Nature, Not Meant For Enforcement Of Conditions Of Contract: JKL High Court
Basit Amin Makhdoomi
6 Dec 2022 11:03 AM IST
![[Arbitration & Conciliation Act] Proceedings U/S 9 Interim In Nature, Not Meant For Enforcement Of Conditions Of Contract: JKL High Court [Arbitration & Conciliation Act] Proceedings U/S 9 Interim In Nature, Not Meant For Enforcement Of Conditions Of Contract: JKL High Court](https://www.livelaw.in/h-upload/2022/09/20/750x450_435912-justice-wasim-sadiq-nargal-jammu-and-kasmir-and-ladakh-high-court.jpg)
Next Story
6 Dec 2022 11:03 AM IST
The Jammu and Kashmir and Ladakh High Court on Monday ruled that final relief cannot be granted under Section 9 of the Arbitration and Conciliation Act, 1996 as proceedings under the said provision are of interim measure and are not meant for enforcement of the conditions of the contract, which can be done only when the rights of the parties are finally adjudged or crystallized by...
Your support helps us to bring you more content at
an affordable subscription scheme !!!
All payment options available