'Shocking The Conscience' Not Enough To Modify Arbitral Award: Supreme Court Restores Contractor's Claim Against Kolkata Port Trust
Yash Mittal
20 Nov 2026 3:48 PM IST

The Supreme Court has set aside a Calcutta High Court judgment that reduced an arbitral award in favour of a dredging contractor by 50%, holding that a court exercising jurisdiction under Section 37 of the Arbitration and Conciliation Act, 1996, cannot interfere with an award merely because the amount granted for additional work appears excessive.
The Court held that the High Court's conclusion that the claim for additional work, which exceeded 70% of the original contract value, shocked its conscience was not a legally sustainable ground for modifying the award.
A bench of Justice J.B. Pardiwala and Justice K. Vinod Chandran set aside a Calcutta High Court Division Bench order that had reduced the arbitral award by 50% on the ground that the amount awarded for additional work exceeded the original contract value by over 70%.
The Court noted that since the additional amount arose from repeated dredging undertaken by the contractor to keep the channel and basin operational, thus, the High Court had mechanically exercised its jurisdiction under Section 37 of the Arbitration and Conciliation Act, 1996, to set aside the award on the mere ground that it exceeded the contract work value merely noting that it shocked the court's conscience without providing a “substantive reason which blatantly and patently brings forth the conflict with the most basic notions of morality or justice, resulting in the conscience of the Court being shocked.”
“…the impugned order has merely used the words on the sole ground of the bills for the additional work having exceeded 70% of the original contract; without looking at the nature of the additional work involved… The Division Bench considering the application under Section 37 has not looked into the measurement or the invoices, which in any event, would be an exercise of adjudication on merits, clearly prohibited under the Act of 1996. The measurements and invoices raised are of one character, based on the additional work of redredging which cannot be compartmentalised as 'valid' and 'invalid'.”, the Court said.
The dispute arose from a contract awarded by the Kolkata Port Trust to Marino Dredgeco for dredging the riverbed and shores at Sagar Island to create an approach channel and basin for a pilot station. During execution, repeated dredging became necessary due to siltation, adverse weather conditions, and differences between the actual soil conditions and the data supplied by the Port Trust. The Port Trust also entrusted additional work through a letter dated July 19, 2000.
After completing the work, the contractor raised additional bills, which led to arbitration. The Arbitrator awarded the claimed amounts, and the Single Judge upheld the award under Section 34. However, the High Court Division Bench, in an appeal under Section 37, reduced the amount by 50% and reduced interest, reasoning that the additional-work claims exceeded 70% of the original contract value and shocked the Court's conscience, following which an appeal was filed by the award holder, Marino Dredgeco, before the Supreme Court.
Allowing the appeal, the judgment authored by Justice Chandran observed that since the additional work, relied upon in an award, was essentially re-dredging of the same channel and basin, the amount involved could not be reduced merely because it was substantial compared to the original contract.
“…we have to observe that the original contract was for dredging to build a channel and the additional work was also for dredging to keep the channel and basin operational. We find the reasoning of the Division Bench under Section 37 to be not in consonance with the grounds provided under the Act to set aside an arbitral award, especially, when the Arbitrator had looked into the documents produced by the petitioner on joint measurements carried out of the additional work entrusted with the contractor.”, the Court held.
“The words are not to be applied on a mere lip service and there should be a substantive reason which blatantly and patently brings forth the conflict with the most basic notions of morality or justice,” the Court said, explaining the standard for holding an award to be contrary to the basic notions of morality or justice.
The Court reiterated that Section 37 does not permit a merits-based review of an arbitral award. It also held that a government entity cannot receive special treatment merely because the amount awarded against it appears excessive.
“There can hence be no interference caused to the quantum of claim decided by the Arbitrator, based on valid material, merely for the reason that the award debtor is a Government entity and that the quantum appears to be excessive without any substantiation for such a ground being raised against the award itself.”, the Court observed.
As a result, the appeal was allowed.
Appearance:
For Petitioner(s) : Mr. R. Anand Padmanabhan, Sr. Adv. Mr. Amitava Mukherjee, Sr. Adv. Mr. Soumya Dutta- 2537, AOR Ms. Reshmi Rea Sinha- 2089, AOR Mr. Rajes Jana, Adv. Ms. Sarbjeet Kaur, Adv. Ms. Shaini, Adv.
For Respondent(s) : Mr. Amitava Mukherjee, Sr. Adv. Mr. Siddharth Bhatnagar, Sr. Adv. Mr. R. Anand Padmanabhan, Adv. Ms. Reshmi Rea Sinha- 2089, AOR Mr. Rajes Jana, Adv. Ms. Sarbjeet Kaur, Adv. Ms. Shaini, Adv. Mr. Udayaditya Banerjee, Adv. Mr. Siddhant Jaiswal, Adv. Mr. Soumya Dutta- 2537, AOR Mr. Siddhant Upmanyu, Adv. Ms. Nisstha Balodia, Adv.