Developer Not Liable To Pay Homebuyer's Bank Loan Interest For Delay In Flat Delivery : Supreme Court
Rizmi Lia
11 Jun 2025 10:35 AM IST

Next Story
11 Jun 2025 10:35 AM IST
In a notable ruling shaping the rights of homebuyers and the liabilities of real estate developers, the Supreme Court has clarified that while developers must refund the principal amount with interest to aggrieved homebuyers in cases of delay or non-delivery, they cannot be held liable for paying interest on the personal loans taken by buyers to finance their homes.A bench of Justice Sanjay...