Six Years Delay In Completing Project, Karnataka RERA Orders Sashwati Realty To Refund
Aryan Raj
7 July 2024 9:30 AM IST

Next Story
7 July 2024 9:30 AM IST
Karnataka Real Estate Regulatory Authority (Authority) bench, comprising GR Reddy (Member), has directed Sashwati Realty, the builder, to refund the amount paid by the homebuyer to purchase a flat, after the builder failed to complete the project even after a six-year delay. Background Fact On 20.08.2014, the homebuyer (Complainant) entered into a sale agreement with the...