Rajasthan RERA Refuses Refund To Homebuyer In Completed Project, Orders Interest For Delay Instead
Aryan Raj
29 May 2024 10:00 PM IST

Next Story
29 May 2024 10:00 PM IST
Rajasthan Real Estate Regulatory Authority (Authority) Bench, comprising Veenu Gupta (Chairperson), refused to grant refund to homebuyer in a completed real estate project, citing potential adverse effects on the project. However, the Authority directed the builder to pay interest to the homebuyer for the delay instead. Background Facts The homebuyer was allotted Flat No. 303...