The Allahabad High Court has observed that when the application for grant of permission for construction has been kept pending by the Greater Noida Industrial Development Authority (GNIDA), the developer cannot be blamed for not constructing flats within the stipulated period in the lease deed.While granting relief to M/s Kinetic Buildtech Pvt. Ltd., petitioner on cancellation of allotment...