The Andhra Pradesh High Court bench of has held the High Court, not being a Court within the meaning of the Arbitration and Conciliation Act, 1996, has no jurisdiction to entertain an application under Section 29A. Section 29A(4) of the Arbitration Act states that if the award is not made within the period specified of six months or the extended period of parties' mutual consent, any...