The Calcutta High Court division bench, comprising Justice I. P. Mukerji and Justice Biswaroop Chowdhury, has upheld the arbitral award amounting to Rs 780 crore in favour of Reliance Infrastructure Limited, with the exception of relief on pre-award interest and reduction in the rate of interest on bank guarantee. The court observed that the grant of pre-award interest was patently...