The Delhi High Court bench of Justice Neena Bansal Krishna held that the question of determination of whether indeed, there was a delay on the part of the Contractor is not an excepted matter and it is only the quantum of damages which is non-arbitrable. The bench held that: “….the question of determination of delay, is not an excepted matter and has to be necessarily arbitrated...