Contract Terminated By An Awardee Following Due Process Cannot Be Subsequently Novated By Awardee Itself: Rajasthan High Court
Nupur Agrawal
27 July 2024 10:30 AM IST

Next Story
27 July 2024 10:30 AM IST
The Rajasthan High Court has ruled that a contract terminated by an awardee following due process cannot be novated by the awardee itself. The Court also held that an administrative order cannot set at nought a duly considered decision or adjudicated order which had bearing on the civil or business rights of contracting parties.A bench of Justice Dinesh Mehta held that "the grant and...