The Rajasthan High Court set aside a commercial court's order passed against a company whose contract for constructing a canal was terminated by the State for allegedly not completing the work. In doing so the high court noted that the commercial court's order was erroneous and based on assumptions as it did not consider the non-performance of the Employer's obligation which went to the "root...