Self-Induced Frustration Amounts To Breach Of Contract, Promisor Obligated To Disclose Inability To Perform Entire Agreement: Telangana HC
Fareedunnisa Huma
29 April 2025 10:00 AM IST

Next Story
29 April 2025 10:00 AM IST
Observing that self-induced frustration of a contract would also amount to its breach, the Telangana High Court underscored that the promisor is obligated to communicate to the promisee on closure of contract at the relevant time being privy to it, and a non-disclosure amounts to disablement of performance under Section 39 of Contract Act. A division bench of Justice Moushumi Bhattacharya...