Electricity Act | Broad Powers Under Section 79 Allow CERC To Act Without Pre-Existing Regulations : Supreme Court
Yash Mittal
16 May 2025 4:21 PM IST

Next Story
16 May 2025 4:21 PM IST
In a notable ruling, the Supreme Court upheld the Central Electricity Regulatory Commission's (CERC) authority under Section 79 of the Electricity Act, 2003, to award compensation for delays in inter-state transmission projects. The bench of Justices J.B. Pardiwala and R. Mahadevan clarified that CERC's power is regulatory, not adjudicatory, and extends to issuing case-specific orders even...
