Limitation Period To Challenge Environmental Clearance Commences From Earliest Date Of Its Public Communication: Supreme Court

Yash Mittal

19 Nov 2025 7:43 PM IST

  • Limitation Period To Challenge Environmental Clearance Commences From Earliest Date Of Its Public Communication: Supreme Court

    If EC was first uploaded on the Ministry's website, then the limitation period will commence from that date, the Court held.

    The Supreme Court ruled that the limitation period for filing an appeal against the grant of Environmental Clearance ("EC") would be reckoned from the earliest date of communication of the EC to the public at large. The Court endorsed the NGT's decision of Save Mon Region Federation & Anr. vs. Union of India, 2013(1) All India NGT Reporter 1 which stated that the "obligations of...