Specific Relief Act | Relinquishment Of Claims Under S.12(3) For Part Performance Can Be Made At Any Stage Of Litigation : Supreme Court

Yash Mittal

13 Jan 2025 11:54 AM IST

  • Specific Relief Act | Relinquishment Of Claims Under S.12(3) For Part Performance Can Be Made At Any Stage Of Litigation : Supreme Court

    The Supreme Court observed that while seeking a part performance of the contract under Section 12(3) of the Specific Relief Act, 1963, the plea regarding the relinquishment of claims regarding the remaining part of the contract and all rights to compensation can be made at any stage of litigation,including the Appellate Stage. “we may only say that the relinquishment of claim to...