Homebuyers Can Claim Interest For Delayed Possession Despite Project Deadline Extension: MahaRERA
Shivani PS
30 Dec 2025 6:10 PM IST

Next Story
30 Dec 2025 6:10 PM IST
The Maharashtra Real Estate Regulatory Authority (MahaRERA) has recently clarified that homebuyers are entitled to interest for delayed possession once the possession date promised in their agreements expires. This holds even if the regulator has extended the project's overall completion timeline. In an order dated December 26, 2025, a coram of Chairperson Manoj Saunik, allowed a batch of...