Interim Measures U/S 9 Of Arbitration Can't Be Sought By MSME During Conciliation Proceedings: Calcutta High Court

Mohd Malik Chauhan

23 May 2025 6:00 PM IST

  • Interim Measures U/S 9 Of Arbitration Cant Be Sought By MSME During Conciliation Proceedings: Calcutta High Court

    The Calcutta High Court bench of Justice Shampa Sarkar has held that interim measures under Section 9 of the Arbitration Act can be sought by the MSME only after mandatory conciliation before the MSME Council fails and the dispute proceeds to arbitration—either conducted by the Council or referred to an arbitral institution. Only then do the provisions of the Arbitration...